Anantara Dragon Seseh Bali Project Marks Major August 2025 Milestones
Updates from the Anantara Dragon Seseh Bali construction site for August 2025 reveal steady progress aligned with the project schedule. Significant achievements were recorded across foundation, piling, earthworks, structural, and concrete phases.
Foundation work advanced as 159 prismatic piles with a total length of 1,232 meters were fully driven. On the left side (RW3), drilling and installation of 131 piles with diameters of Ø800mm and Ø500mm totaling 1,880 meters supported a 127-meter retaining wall. The right side (RW5.1) saw the installation of 110 Ø800mm piles totaling 1,537 meters for a 110-meter retaining wall. Meanwhile, at the rear (RW4), 83 Ø800mm piles measuring 1,328 meters reinforced an 83-meter retaining wall.
Earthworks progressed with the removal of 41,800 cubic meters of soil to shape the site terrain. Structural preparations include the assembly of a framework reaching 121 meters in height with a wing span of 64 meters, indicating the scale of the development. Concrete operations contributed over 1,700 square meters of lagging concrete, ensuring solid ground fixation and stability.
These milestones underscore steady advancement toward establishing a unique architectural symbol in Bali. The project team invites stakeholders and interested parties to stay tuned as more exciting construction phases unfold.